Manufacturing / Aerospace

GE Aerospace: Forecasting aircraft engine maintenance parts and placing orders earlier

Company
GE Aerospace
Country
Brazil
Adoption stage
Limited operation
Source published
Date basis
The date the source was published. It can differ from the date adoption started.
How the source was checked
Read the full source text

The work problem

Distance from US suppliers meant parts shortages delayed engine redelivery at GE Aerospace's Celma shop in Brazil. Expanding LEAP servicing required anticipating parts before inspection.

Technology and data

AIMA analyses engine operation, configuration, shop history, expected work and inventory. It evaluates around 300 parameters per engine and connects to enterprise systems to automate selected planning and earlier ordering. Materials staff helped design it; planners use signals before induction.

Results

GE Aerospace reported improvements of 24% in on-time orders, 25% in ordering within catalog lead time and 13% in on-time delivery in Celma's LEAP pilot. These describe proactive parts planning, not total engine turnaround reduction.

Limits and open questions

Measurement periods, samples and improvement formulas were undisclosed. Expansion to other engine lines remains planned.